Sprint 2 - 26/01/26 - 01/02/26
This document describes the main goals of the second sprint of TB2 and reflections on the past week:
Reflecting on Sprint 1 of TB2
- Clarified with client what feedback is expected.
- Completed meetings with client, mentor and Sarah
- Completed data collection session on the 23rd
- Completed first prototype mount for the radar
- Compiled notes from meetings and added the relevant information on Docusaurus
- Successfully Implemented a camera section to the industrial visualizer.
- Fixed issues with data formats in data collection.
- Made significant progress to the overall goals of the project.
- Overall team communication has improved significantly.
- Thanks to having a dedicated PM meetings are now much more effective and efficient. Outcome: Sprint 1 agenda completed.
Sprint 2 agenda:
- Tom: Remove buffers from collected data and attempt to plot it out.
- Tom and Michal: Test current model with collected data.
- Dan: Continue working on camera functionality with the Industrial visualizer
- Alina and Michal: Implement data recording functionality to the industrial visualizer via a button so that we can start and stop at which will increase data collection efficiency.
- Alina and Michal: Discuss data collection session to find areas of improvement.
- Henry: Plan next sprint’s agenda and complete PM tasks
- Talal: Plan and start organizing the repository to match learning outcomes.
- Henry and Talal: Continue working on the 3d printed mount for the camera.
- Entire Team: Meeting with mentor Jack on Tuesday
- Entire Team: Data collection session on Friday
- Entire Team: Standup to discuss Sprint 2 on Friday
- Entire Team: Prepare and plan for Testing day.
The agenda listed above is the focus of the sprint but not the entire list of tasks that have been or will be completed.